Full steam ahead: New four-story patient tower takes shape

Mike Scott, mscott@stph.org

The new patient wing at St. Tammany Health System's main hospital campus rises along South Tyler Street.  (Photos by Tim San Fillippo / STHS)

Coordinating the construction of a four-story structure at the same time you’re running a full-service hospital is never exactly an easy task. Doing it in the middle of a global pandemic only makes things that much more difficult. 

Yet, despite the challenges, work on St. Tammany Health System’s new patient wing – ground for which was broken in 2018 and which is part of a three-year, $100 million expansion plan – continues apace, with a ribbon-cutting ceremony expected to take place this winter. 

Below, find photos taken inside the building, which was designed by the Covington-based fl+WB Architects to blend seamlessly with the existing building – and which was teeming with activity recently as crews with Womack Construction put finishing touches on everything, literally, from the floors to the ceilings. 

As with much of the new wing’s first floor, the elevator lobby is tiled with a light brown marble tile. The ground-level flooring, when completed, will be poured terrazzo.

The ceiling treatment in public areas on the first floor, including in this Administration conference room, will feature arched wood panels. 

Crews work on the lighting in the Administration reception area.

Cabinetry is already installed in an administrative area.

A little impromptu artwork adds a bit of levity to the work site.

ABOVE: Some of the tools of the trade are arrayed in front of a wall featuring glass tiles arranged in a herringbone pattern.





BELOW: A nursing station takes place in one of the patient areas, which will occupy the second and third floors.

ABOVE: Distinctive, eye-catching lighting is featured in a number of areas of the new building.  

RIGHT: A look down the first-floor hallway that will connect the new wing to the old building near the current site of PJ’s Coffee. 

BELOW: The fourth-floor, reserved for future expansion, will remain largely unfinished initially.

Featured Videos

Video

Healthy Living with Mike McNeil | April 2024

Mike McNeil, Director of Outpatient Rehab Services with St. Tammany Health System discusses all things outpatient therapy,...

Tuesday, Apr 30, 2024

Video

Healthy Living with Mike McNeil | April 2024

Mike McNeil, Director of Outpatient Rehab Services with St. Tammany Health System discusses all things outpatient therapy,...

Tuesday, Apr 30, 2024

Video

Healthy Living with McCall McDaniel MD | April 2024

Dr. McCall McDaniel - Pediatric Orthopedic Specialist, with the St. Tammany Health System Bone and Joint Clinic discusses...

Monday, Apr 22, 2024

Video

Healthy Living with McCall McDaniel MD | April 2024

Dr. McCall McDaniel - Pediatric Orthopedic Specialist, with the St. Tammany Health System Bone and Joint Clinic discusses...

Monday, Apr 22, 2024

Video

Celebrate Differences

In recognition of April as World Autism Acceptance Month, St. Tammany Health System is doing its part to accept and welcome...

Monday, Apr 15, 2024

Video

Celebrate Differences

In recognition of April as World Autism Acceptance Month, St. Tammany Health System is doing its part to accept and welcome...

Monday, Apr 15, 2024

Connect