Parking Garage Progress

STHS parking garage progress

As St. Tammany Health System's parking garage project along South Tyler Street takes shape, we will post regular construction updates to this page.
Check back regularly for progress reports as they are available.




April 1, 2026: A crane rises over the site of the future STHS parking garage on Wednesday, April 1, 2026. Crews will be using the crane to install auger-cast test piles -- which require no pounding -- as construction ramps up. (STHS photo)

March 30, 2026: Crews position a crane that will be used to install auger-cast test piles -- which require no pounding -- on the site of the future St. Tammany Health System parking garage, as seen Monday March 30. (STHS photo)

March 26, 2026

A bird’s-eye view of the site of the future St. Tammany Health System parking garage, as seen Thursday, March 26, 2026. Sheet piles have been installed around the privately owned Tchefuncte Urgent Care building, and construction fencing rings the perimeter of the garage site while dirt work continues. (STHS photo)

Site preparation continues on the STHS parking garage project at the corner of West 11th Avenue and South Tyler Street, with dirt work (grading) continuing ahead of the commencement of construction. Here’s what colleagues and neighbors can expect in coming days and weeks:

  • In coming days, a crane will arrive on-site to begin installation of a series of auger-cast test piles both on the garage site and across W. 11th Avenue, on the hospital side of the street. (This type of pile requires no pounding and thus produces no vibration and little noise compared to traditional piles.)
  • As part of the test pile process, the crane will be required to cross 11th Avenue, to the hospital side of the street.
  • Also on the hospital side of W. 11th Avenue, a new stairwell egress will be installed in coming weeks at the corner of 11th and S. Tyler Street – with a new, temporary sidewalk leading from it – to ensure public and colleague safety as work continues on that corner of the building to prepare it for the eventual tie-in of a pedestrian skybridge connecting the garage to the hospital.
  • In coming weeks, crews will demolish the two-story masonry outcropping and STHS logo on the corner of S. Tyler and 11th Avenue, just outside the hospital’s Radiology Department, to provide clearance for the skybridge. The skybridge has been designed to match the style and design of the existing skybridge over Tyler and to harmonize with the main hospital building.


An aerial view of the future home of the STHS parking garage, taken on March 16, 2026. (STHS photo)

The same section of the work site, as photographed on March 19. (STHS photo)

March 19, 2026: Site preparation is well underway on the STHS parking garage project at the corner of West 11th Avenue and South Tyler Street, with dirt work (grading) continuing ahead of the commencement of construction. Here’s what colleagues and neighbors can expect in coming days and weeks:

  • Installation of sheet piles will begin in coming days around Tchefuncte Urgent Care on West 11th Avenue to protect it during construction. This work is estimated to last about four days once it starts, barring any delays.
  • In coming weeks, observers will see a crane arrive on the work site. The crane will be used to install a series of auger-cast test piles. (This type of pile requires no pounding and thus produces no vibration and little noise compared to traditional piles.)
  • Also in coming weeks, hospital colleagues should plan for the closure of the small parking lot along South Tyler just outside the hospital’s Radiology Department as crews prepare the hospital building for the tie-in of a skybridge that will eventually connect the garage to the hospital.
  • Activity will continue at the now-vacant future site of the STHS women and children’s facility just south of the hospital on Louisiana 21, which will be used for staging of construction equipment for the garage project.


March 12, 2026

PHOTO OF THE DAY: As part of their site preparation work, crews added a construction trailer to the site of the future STHS parking garage on Thursday, March 12, 2026. (STHS photo). (STHS photo)

Site preparation continues on the STHS parking garage project, with construction fencing and blue windscreen now completely ringing the site. In coming weeks, colleagues can expect to see:

  • Dirt work will continue ramping up ahead of any structural work, with fill delivery expected on-site as early as next week.
  • Sheet piles are still forthcoming around the independently operated urgent care across W. 11th Avenue from St. Tammany Parish Hospital to protect it during the construction process.
  • Auger-cast test piles, which will create no pounding or vibrations, are still planned on the garage site before construction begins in earnest.
  • Windscreen will be installed on the now-complete construction fencing around the largely vacant future site of the STHS Women and Children’s facility just south of the hospital on Louisiana 21, which will be used for staging of construction equipment for the garage project.
  • As always, colleagues are reminded to park only in designated parking spots and to always respect construction cones, tape, fencing, etc.


March 5, 2026

PHOTO OF THE DAY: An aerial view of the site of the future STHS parking garage, as seen from St. Tammany Parish Hospital on Thursday, March 5, 2026. (STHS photo)

Site preparation continues on the STHS parking garage project. In coming weeks, you can expect to see:

  • Windscreens installed on the construction fencing ringing the site perimeter.
  • Additional site work, including the use of dirt fill, to further prepare the site for construction.
  • Installation of auger-cast test piles. (These piles require no pounding and thus produce no vibration.)
  • Installation of sheet piles around the privately owned urgent care facility located across W. 11th Avenue from the main campus Emergency Department (at center of image above), to protect it during construction.
  • Removal by utility companies of the utility poles on the garage site, all of which have been disconnected.
  • Installation of temporary construction fencing around the largely vacant future site of the STHS women and children’s facility just south of the hospital on Louisiana 21, which will be used for staging of construction equipment for the garage project.


Feb. 26, 2026: - With demolition of the old Northlake Surgical Associates facility entering the “cleanup” phase, neighbors can expect to soon see more site-preparation activity on the parking garage site starting as early as Monday. This includes:

  • Installation of auger-cast test piles.
  • Asphalt removal.
  • Grading of the garage site.
  • Other, related work.


Feb. 24, 2026: Crews begin removal of the old concrete foundation on the site of the demolished former Northlake Surgical Associates building, as seen Tuesday, Feb. 24, 2026, along with performing other cleanup from the building's demolition last week.

Feb. 20, 2026: Crews complete demolition of the former Northlake Surgical Associates practice, which was located on the future site of the parking garage. The accompanying photo shows the Northlake Surgical site around midday on Friday, Feb. 20 -- after demolition of the structure.

Feb. 7, 2026: Crews begin site mobilization. This will include:

  • Installation of fencing around the construction area.
  • Installation of stormwater protection infrastructure.
  • Demolition of the building that previously housed Northlake Surgical and Associates.
  • Installation of a test pile. (Of note: In deference to neighbors and hospital patients, the garage project will utilize auger-cast piles, which consists of drilling a hole and filling with steel cage and concrete – and which notably does not involve hammering or vibration.)

Jan. 12, 2026: To accommodate garage construction, St. Tammany Health System's Northlake Surgical Associates practice has relocated to 728 W. 11th Ave, just one block from its previous home on the site of what will become the garage. 


May 2024:  After years of planning and study, St. Tammany Health System announces to its colleagues that it is taking the first steps toward building a new parking garage to serve its flagship St. Tammany Parish Hospital in Covington. The five-level parking structure, to be located across W. 11th Ave. from the hospital's Emergency Department, is designed to serve the hospital's growing parking needs and provide a rooftop helistop closer to its Emergency Room, giving our team precious additional minutes in a critical care situation. 


Below is an artist's rendering of the new structure, which was designed to harmonize aesthetically with the existing hospital building and the pedestrian Skybridge over S. Tyler Street.